The Tribe seeks comments on the Antidegradation Decision for the proposed Miller Road Culvert Replacement Project. This project involves replacing under sized culverts that do not have the capacity to handle large volumes of water due to spring thaw and large storm events within the external boundaries of the Bad River Reservation (Reservation). A total of three culverts will be removed along with four larger culverts being installed. Activities associated with this project include; clearing and grubbing, excavation and back filling, placing geo text tile fabric and light rip rap, refinishing the roadway, seeding and fertilizing, and placement of erosion control methods. A total of 0.14 acres (6098.4 sq. ft.) of temporary wetland impacts will be the result of this project. (Read More)